5-103. Reforestation.
(a) Definitions - (1) In this section
the following words have the meanings indicated.
(2) "Construction activity" means
construction of a highway by a constructing agency.
(3) "Constructing agency" means:
(i) A unit of State or local government;
or
(ii) Any other person who uses State
funding and performs any construction activity with the State funding.
(4) (i) "Forest" means a biological
community dominated by trees or other woody plants covering a land
area of 1 acre or more.
(ii) "Forest" includes an area that
has been cut but not cleared of trees or other woody plants.
(5) "Watershed" means all lands
lying within an area described as a sub-basin in water quality regulations
adopted by the Department of the Environment.
(b) Government to minimize cutting
or clearing. - To accomplish a construction activity involving land
clearing, a unit of State of local government or any other person
using State funding for the construction project:
(1) May cut or clear only the minimum
number of trees and other woody plants that are necessary and consistent
with sound design practices; and
(2) Shall make every reasonable
effort to minimize the cutting or clearing of trees and other woody
plants.
(c) When required. -(l) If the total
area of forest cut or cleared in connection with a construction
activity by a unit of State or local government or any other person
using State funding for the construction project equals 1 acre or
more, the constructing agency shall locate an equivalent area of
State owned or other publicly owned land to be reforested by the
Department at a rate of 10 cents per square foot of the area of
required planting.
(2) (i) Except as provided in subparagraph
(ii) of this paragraph, the reforestation projects shall be established
on any public land within the county and watershed in which construction
activity by a unit of State or local government has caused a loss
of trees where the public entity that owns the land egress to that
use of the land.
(ii) If the reforestation project
cannot be reasonably accomplished in the county and watershed in
which the construction activity is located, then the reforestation
shall occur in the county or watershed in the State in which the
construction activity is located.
(3) The constructing agency shall
reimburse the Department for the reforestation activities at an
appropriate rate of 10 cents per square foot of the area of required
planting.
(4) Any land for a reforestation
project shall be:
(i) If possible, on the site
or in the project right-of-way being used for the construction activity;
(ii) If sufficient area is not available
at the site or within the project right-of-way, on State owned or
other publicly owned land in the county and watershed in which the
construction activity is located; or
(iii) If the reforestation project
cannot be reasonably accomplished in the county and watershed
in which the construction activity is located, on State owned or
other publicly owned land in the county or watershed in the State
in which the construction activity is located.
|